Management of the Projects
Conclusion of project’s completion

Upon completion and delivery of the project (economic and physical object) the Implementation Institution sends a letter to the SMA to inform it about the project’s completion.

Once the SMA receives the letter of the FB confirming the completion of the project, Unit B sends to Unit C an “Application for the establishment the completion of the project”. This includes on site inspection of the qualitative, economic and operational results of the act. Moreover, it asks Unit C to confirm the observance of the obligations by the FB.

Unit C conducts an on site inspection and concludes that the project is completed.

Conclusion of project’s completion

The SMA makes a Proposal of the Project’s Completion and then reaches the Conclusion of the Project’s Completion.

The decision is taken after the FB has submitted the following:

  • Either the TSP
  • Or the last Quarterly Report confirming the completion of the physical and economic object.